Ganttproject allows you to specify a relationship between two tasks. You can set them by using drag directly on the chart. Click and hold on the first task and motion to the second task. An arrow will appear, following the mouse. Drag the arrowhead to th
e second task and release the mouse. The second task will be dependent on the first one.
You will have a chart like this:
Figure 4:
Create relationship between tasks
|